For fiscal year July 1, 2001 - June 30, 2002, the City of
Fontana Redevelopment Agency completed the following project
activities:
Downtown Redevelopment Project
All of the anticipated Fiscal Year 2001/2002 tax increment
was committed to debt service payments. There was no available
funding for new redevelopment projects for the Downtown Project
Area. However, Agency staff worked with the Downtown Revitalization
Task Force to assist them in establishing a vision for the
future of the central part of the City. Additionally, significant
investment in developing the Civic Center campus was made
in Fiscal Year 2001/2002.
Total expenditures of capital projects funds amounted to
$107,734.00:
| Contribution for Lease Reimbursement |
$ 27,934.00 |
| Interest Expense |
$ 79,800.00 |
| Total Expenditures |
$ 107,734.00 |
Jurupa Hills Redevelopment Project
The Fiscal Year 2001/2002 budget provided for the continued
monitoring and implementation of the OPA, Facilitation Agreement,
Development Agreement, Second Agreement and the various other
linked agreements between the Agency, City, and the Master
Developer (Ten-Ninety, LTD) to ensure compliance and to avoid
potential costly litigation and legal expenses.
Although not directly funded by Agency revenues, staff worked
on an important "Robert W. Weddle Capital Improvement Project"
that did benefit the Project Area. The project included the
design and of the north side of Jurupa Avenue to its full
right-of-way from Sierra Avenue west to Mulberry Avenue.
Total expenditures of capital projects funds amounted to
$1,626,459.00:
| Rents & Leases |
$ 6,000.00 |
| Legal Services |
$ 15,740.00 |
| Project Improvement/Construction Costs |
$ 1,477,455.00 |
| Interest Expense |
$ 81,538.00 |
| Contribution for Lease Reimbursement |
$ 45,726.00 |
| Total Expenditures |
$ 1,626,459.00 |
North Fontana Redevelopment Project
In Fiscal Year 2000/2001, the Redevelopment Agency sold five
(5) acres of commercial property to a mid western hotel chain
for construction of a business-class hotel and restaurant
facilities. The hotel was actually constructed and opened
in Fiscal Year 2001/2002.
There was a significant amount of residential development
that took place in North Fontana. The significant residential
growth has resulted in substantial tax increment revenues
that allowed for the refinancing of existing bonds and the
creation of capital funds for new projects. These projects
included the Baseline Storm Drain and Street Improvements,
Summit Avenue Utility and Street Improvements, San Sevaine
Multi-purpose Trail, and the Sierra Avenue Street Improvements.
Total expenditures of capital projects funds amounted to
$1,103,449.00:
| Administration Costs |
$54,052.00 |
| Operating Expenditures |
$ 898,127.00 |
| Contractual Services |
$ 64,915.00 |
| Project Improvement/Construction Costs |
$ 86,355.00 |
| Total Expenditures |
$ 1,103,449.00 |
Sierra Corridor Redevelopment Project
No capital projects were constructed in Fiscal Year 2001/2002.
The Fiscal Year 2001/2002 revenues to the extent available,
were utilized to assist in implementing the workout strategy
for the Empire Center. Staff and its team of consultants mounted
an intensive effort to resolve all financial issues and land
use element such that the City could convey the land to a
private developer in the near future.
Total expenditures of capital projects funds amounted to
$90,684.00:
| Operating Expenditures |
$ 88,638.00 |
| Contractual Services |
$ 2,046.00 |
| Total Expenditures |
$ 90,684.00 |
Southwest Industrial Park Redevelopment
Project
There has been significant industrial growth in SWIP resulting
in greater tax increment revenues for the Agency, jobs for
the people, and general revenue for the City. The Agency's
most recent project in SWIP was the completion of the Auto
Mall. The Agency sold 27.53 acres of land to Sunrise Management
Company for the relocation and development of a Ford dealership
and several additional franchises. Required infrastructure
construction by the Agency to serve the general area of the
Auto Mall area was completed. Looking to the future, the focus
of the Agency efforts in Fiscal Year 2001/2002 was to:
1). Evaluate and develop the economic potential of the Valley
Boulevard Corridor (the northern portion of SWIP); and
2). Final construction of a key segment of the San Sevaine
Flood Control System (Jurupa avenue south to Philadelphia).
Total expenditures of capital projects funds amounted to
$1,405,061.00:
| Administration Costs |
$ 54,052.00 |
| Operating Expenditures |
$ 1,065,154.00 |
| Contractual Services |
$ 151,002.00 |
| Project Improvement/Construction Costs |
$ 134,853.00 |
| Total Expenditures |
$ 1,405,061.00 |
|