For fiscal year July 1, 2000 - June 30, 2001, the City of Fontana Redevelopment Agency completed the following project activities:

Downtown
Due to existing financial obligations, no capital projects were constructed during the fiscal year.

Jurupa Hills
Due to existing financial obligations in all project areas, no capital projects were constructed during the fiscal year 2000-2001.

Total expenditures of capital projects funds amounted to $1,272,145.00:

Administration Costs $ 58,485.00
Professional Services $ 1,098.00
Project Improvement/Construction Costs $ 1,131,024.00
Interest Expense $ 81,538.00
Total Expenditures $ 1,272,145.00

North Fontana
Due to existing financial obligations in all project areas, no capital projects were constructed during the fiscal year 2000-2001. A park, community center, major thoroughfare and street improvements, and a fire station have been deferred due to lack of funding.

Total expenditures of capital projects funds amounted to $4,030,296.00:

Administration Costs $ 36,861.00
Professional Services $ 58,118.00
Project Improvement/Construction Costs $ 3,935,317.00
Total Expenditures $ 4,030,296.00

Sierra Corridor
Due to existing financial obligations in all project areas, no capital projects were constructed during the fiscal year 2000-2001.

Total expenditures of capital projects funds amounted to $99,468.00:

Administration Costs $ 7,300.00
Professional Services $ 5,505.00
Project Improvement/Construction Costs $ 86,663.00
Total Expenditures $ 99,468.00

Southwest Industrial Park
In fiscal year 2000-2001 a variety of activities related to the Auto Mall occurred. Negotiations, financial activities, engineering design, and other tasks were performed.

Total expenditures of capital projects funds amounted to $4,665,209.00:

Administration Costs $ 1,719,313.00
Professional Services $ 166,646.00
Planning, Survey & Design $ 1,809.00
Acquisition Expense $ 2,975.00
Project Improvement/Construction Costs $ 2,774,466.00
Interest Expense $ 81,538.00
Total Expenditures $ 4,665,209.00

.........................................

 

 

In this section:
::
::
::
::
::
::
  2000-2001
  2001-2002
  2002-2003
  2003-2004
  2004-2005
  2005-2006
  2006-2007
  2007-2008
  2008-2009